Gulf Power Accelerates Plans To Switch Plant Crist To Natural Gas Delivered Through North Escambia Pipeline
November 11, 2020
Gulf Power is accelerating plants to switch Plant Crist to natural gas delivered by a pipeline through North Escambia.
Tuesday, Gulf Power notified the Florida Public Service Commission that it plans to retire the plant’s coal assets early and switch to 100% natural gas. That, the company says, will result in benefits to the local community as well as cost savings for customers.
Converting coal-burning units to run on natural gas is a major piece of the modernization underway at Plant Crist, along with the addition of four new, highly efficient combustion turbines to provide greater reliability and efficiency for the energy grid and a new natural gas pipeline to provide additional natural gas for the plant. By eliminating the use of coal at Plant Crist, Gulf Power will reduce the plant’s carbon emissions rate by 40% – the equivalent to taking an estimated 297,000 cars off the road annually – and reduce operating costs for customers.
Over the past several months, Gulf Power has installed an underground natural gas pipeline that runs 39 miles from the Florida Gas Transmission Pipeline near Century, through McDavid, Molino and Cantonment, to the company’s Plant Crist.
The retirement of coal at Plant Crist was accelerated by Hurricane Sally, which caused damage to the plant’s coal equipment. The company determined that it is in the best interests of its customers to accelerate the modernization instead of repairing the coal equipment.
“Retiring coal at Plant Crist will end our use of coal in Florida and help usher in a new, cleaner energy era for Gulf Power,” said Marlene Santos, president of Gulf Power. “Ending our use of coal delivers benefits for our customers and our communities through lower costs along with cleaner emissions. We look forward to continuing to invest in cleaner energy solutions for Northwest Florida, including more efficient natural gas technology as well as emissions-free solar farms.”
Gulf Power is seeking approval to adjust the company’s Environmental Cost Recovery Clause (ECRC) factor for 2021 to reflect the savings associated with the early retirement of coal at Plant Crist and to begin recovering storm restoration costs for Sally. If approved by the FPSC, both adjustments to customer bills would likely take effect in March 2021 and result in a net decrease in the typical residential customer bill of $0.73.
Pictured top: Bright yellow new pipes threaded throughout the inside and outside of Plant Crist this year are the visible signs of the coal to natural gas conversion that will allow the plant to run 100% on U.S. produced natural gas. Pictured inset: A crane hoists one of the larger pieces of new equipment at Plant Crist, a gas heater, into place at the Plant Crist gas yard as part of the coal to natural gas conversion. The heater will warm the natural gas to keep it from freezing in the pressure control valves that send the gas from the pipeline to the power plant. Courtesy photos for NorthEscambia.com, click to enlarge.
"gas" - Google News
November 12, 2020 at 01:58PM
https://ift.tt/2Uh37pZ
Gulf Power Accelerates Plans To Switch Plant Crist To Natural Gas Delivered Through North Escambia Pipeline - NorthEscambia.com
"gas" - Google News
https://ift.tt/2LxAFvS
https://ift.tt/3fcD5NP
Bagikan Berita Ini
0 Response to "Gulf Power Accelerates Plans To Switch Plant Crist To Natural Gas Delivered Through North Escambia Pipeline - NorthEscambia.com"
Post a Comment